Harbour Business Centre: refurbishment
Input: Cap Ex approval CE-2026-014 (£850,000 incl. £40,000 contingency), tender analysis report, valuations 1 to 4
| Item | Cap Ex | Forecast | Variance | Flag |
|---|---|---|---|---|
| Preliminaries | £95,000 | £102,500 | +£7,500 | Over |
| Roof replacement | £310,000 | £296,800 | −£13,200 | Under |
| Windows and doors | £180,000 | £174,300 | −£5,700 | Under |
| M&E | £225,000 | £241,900 | +£16,900 | Over |
| Asbestos removal | £0 | £18,600 | +£18,600 | Not in budget |
| Total (before contingency) | £810,000 | £834,100 | +£24,100 |
- Missing scopeExternal lighting is in the Cap Ex spec but excluded from the M&E tender (tender report p.14). Not yet priced.
- Invoice errorValuation 4 retention taken at 3%, contract says 5%. Overpaid £2,140.
of contingency used (£24,100 of £40,000)
issues to resolve before final account