Dilapidations vs priced works
Unit 7, Deans Industrial Estate: lease end
Input: schedule of dilapidations (PDF, 14 March 2026) and contractor’s priced works (spreadsheet, rev C)
| Item | Dilaps claim | Priced works | Gap | Result |
|---|---|---|---|---|
| Clean and repair gutters | £1,200 | £1,450 | £250 | Matched |
| Replace damaged cladding panels | £8,400 | £9,900 | £1,500 | Matched |
| Redecorate external steelwork | £3,600 | £4,100 | £500 | Matched |
| Repair yard surface | £5,500 | £7,800 | £2,300 | Matched |
| Replace roller shutter door | £4,200 | n/a | n/a | Dilaps only |
| New drainage gully | n/a | £2,300 | £2,300 | Works only |
| Total | £22,900 | £25,550 | £6,850 |
shortfall on the works you’re doing
claimed but not in your works: check before negotiating